Student Housing Phase 1 & 2

ecomm2Construction Web Cam Photo

(Phased construction of  5 Student Housing Units South of Euclid Avenue)
South of Euclid at East 24th Street
Project Number: LF-0811  Phase 1 & 2

Current Status:

Phase 1 complete and occupied
Unit 4 to be ready for occupancy August 2011

Phase 1  (322 Beds)  (100%)
Completed buildings 1, 2, 3 and parking garage.
Prime Contractor: Marous Brothers
Construction Manager: American Campus Communities

Phase 2  (269 Beds)  (55%)
Completed buildings 4 and 5.
Prime Contractor: Marous Brothers
Construction Manager: American Campus Communities

Time Frame

Construction Start Date Phase 1: August 2009
Completion Date Phase 1: August 2010

Construction Start Date Phase 2: August 2011
Completion Date Phase 2: August 2012

Description of Work

Individual housing units will feature living space and kitchens ad contain: dining table and chairs, full size refrigerator, over the range microwave, range, dishwasher, cabinets, sink with garbage disposal, entertainment center, coffee tables, end tables and soft seating in the form of couches and lounge chairs to accommodate the number of beds.  Rooms will include private phone jack, data hook-up and cable connection.

Amenities included within the common area:  A social lounge with gaming, business center, vending area, mailroom, laundry facilities, public restrooms, reception/conference area with managerial offices attached, maintenance office, master trash room and mechanical areas.

The project will also include approximately 16,740 square feet of office space to accommodate the University's Admissions Office, Marketing Office and Parking Office.  The four story parking facility will accommodate 295 parking spaces.

 

Project Team

Construction Manager
American Campus Communities

Design Architects
Weber Murphy Fox

Planning Consultants
ACC

CSU Staff
Project Manager: Melanie Boyd
University Architect: Ed Schmittgen

Projected to achieve LEED Silver Certification:
   Abatement & Demolition of Old Book Store
   Construction Waste Management up to 80% diverted from land fills
   Natural Daylight throughout the buildings
   Views from every major interior space
   Recycled content in building materials (carpet, drywall,ceilings, etc.)
   Low VOC paints and coatings

Awards

Projected Silver LEED
2011 Downtown Cleveland Development Award

Budget

Project Budget: $57,000,000
Construction Budget: $45,000,000

Financing

Bonded

Date Last Updated: October, 2011

engaged learning
Mailing Address
Cleveland State University
2121 Euclid Avenue, PS 235H
Cleveland, OH 44115-2214
Campus Location
Plant Services, Room 235
1802 East 25th Street
Phone: 216.687.5121
Fax: 216.687.9227
architect@csuohio.edu