Complete and closed
Prime Contractor: Lake Erie Electric
Construction Start Date:
5/14/2010
Completion Date: 8/1/2010
Installation of a new power duct bank north of Euclid Avenue between East 22nd Street and East 24th Street.
Design Architects NBBJ
Karpinski Engineering
CSU Staff
Project Manager: Jon Erdmann
University Architect: Ed Schmittgen
Project Budget: $1,100,000
Construction Budget: $ 500,000
Local Funding
© 2013 Cleveland State University | 2121 Euclid Avenue, Cleveland, OH 44115-2214 | 216.687.2000