Campus Safety Building (CS)
1870 East 19th Street
Project Number: CP-0603A

Current Status: Construction Complete

Prime Contractor: Sterling Professional Group
Construction Manager: University Architect's Office

Time Frame

Construction Start Date: March 12, 2010
Completion Date: March 31, 2011

Description of Work

Renovate the existing Baker's Union Building into the new Campus Safety Building. Relocate the Police department from Chester Annex utilizing the basement and fist floor.

Project Highlights

Project Team

Construction Manager
University Architect's Office

Design Architects
Ziska Architecture

Planning Consultants
Karpinski Engineering, RCS Environmental and Polytech

CSU Staff
Project Manager: Tania Anochin

University Architect: Ed Schmittgen

Received conditional certification of Occupancy.  Police and Security begin moving in April 2011 with dispatch moving in May 2011.

A New glass and steel entrance on Chester Avenue giving the police force a wonderful campus presence. A new, state of the art dispatch is a major component on the first floor. The county mobile emergency response unit is docked at this location.

 

Budget

Project Budget: $3,123,500
Construction Budget: $2,267,107

 

Financing: 

Capitol funding

Last Updated: April 2011

engaged learning
Mailing Address
Cleveland State University
2121 Euclid Avenue, PS 235H
Cleveland, OH 44115-2214
Campus Location
Plant Services, Room 235
1802 East 25th Street
Phone: 216.687.5121
Fax: 216.687.9227
architect@csuohio.edu


This site contains files that require the free Adobe Reader to view.